Every client, builder, bid, price, and finding below is invented to show the report format. No real company or person is described. Benchmark figures in this sample are illustrative placeholders, not market data; real reports cite a public source for each benchmark.
Prepared by Lucan Ashvere (operated by MB Skydis) · Report ID: SAMPLE-0001 · Tier: Bid + Contract Review ($795)
Independent document and price analysis. AI-assisted and checked against a fixed checklist. Not engineering, inspection, or legal advice.
| Item | Detail |
|---|---|
| Client / location | "Sample Homeowner", fictional suburb, Sun Belt state |
| Pool | Gunite, ~15×32 ft freeform, 3.5–6 ft, ~22,000 gal, attached spillover spa |
| Features | Heat pump, LED lights, automation, travertine deck |
| Stated budget | $95,000 |
| Bids | Bluefin Pools (fictional): $92,400 · Coral Coast Builders (fictional): $86,900 · Summit Aquatics (fictional): $104,750 |
| Documents | 3 proposals (4, 2, 9 pages), Bluefin contract (11 pages), Summit 3D design |
| # | Finding | Bid | Est. $ impact | Action |
|---|---|---|---|---|
| 1 | Decking quoted at 400 sq ft vs. 650 sq ft in the others | Coral | +$7,500–$10,000 to match | Ask for 650 sq ft price |
| 2 | Rock excavation billed "at cost" with no cap | Bluefin | Open-ended | Request cap or per-hour rate + max |
| 3 | 40% due at excavation (before steel/shell) | Bluefin | Cash-flow risk | Propose milestone-tied draws |
| 4 | Electrical and gas lines "by others" | Coral | +$4,000–$7,000 (sub quotes needed) | Get separate quotes before comparing |
| 5 | Heat pump not specified by model or BTU | Coral | Unknown | Ask model and output rating |
Overall: after normalizing scope, Coral's apparent $5,500 advantage over Bluefin likely disappears. Summit is the most complete and most expensive; its premium is mostly a larger spa and upgraded finish. This is not a hiring recommendation.
| Scope item | Bluefin | Coral | Summit | Note |
|---|---|---|---|---|
| Excavation & haul-off | Included | Included | Included | |
| Rock clause | At cost, no cap | $X/hr, cap $3,000 | Included up to 4 hrs | Bluefin open-ended |
| Steel | #3 rebar 10" OC | "Per engineering" | #4 rebar 10" OC | Ask Coral for spec |
| Plumbing | 2" suction, 4 returns | Not stated | 2.5" suction, 5 returns | |
| Pump | Variable speed (model listed) | "VS pump" | Variable speed (model listed) | |
| Filter | Cartridge 420 sq ft | Cartridge (size n/a) | Cartridge 520 sq ft | |
| Heater | Heat pump (model listed) | "Heat pump" | Heat pump (model listed) | |
| Interior | Standard plaster | Standard plaster | Pebble-type finish | Summit upgrade |
| Decking | 650 sq ft travertine | 400 sq ft travertine | 650 sq ft travertine | |
| Electrical / gas | Included | By others | Included | |
| Permits / engineering | Included | Permit only | Included | |
| Barrier / alarms | Not mentioned | Not mentioned | Door alarms included | Check local code |
| Startup & orientation | 30 days | Not stated | 60 days | |
| Warranty | Shell lifetime*, 1 yr workmanship | 1 yr | Shell 10 yr, 2 yr workmanship | *read exclusions |
| Line item | Bluefin | Coral | Summit | Reference | Source |
|---|---|---|---|---|---|
| Decking per sq ft | $28 | $27 | $30 | [real report: cited public range] | [URL] |
Bluefin and Summit list model numbers; their published filter ratings exceed the stated pump flow, which is the normal relationship. Coral lists generic categories only, so no comparison is possible until models are supplied. (Spec comparison only, not engineering.)
| Clause | Finding | Risk | Suggested wording |
|---|---|---|---|
| §3 Payment | 10% deposit, 40% excavation, 30% shell, 20% completion | High | "Draws payable on completion of each listed stage, with final 10% after startup and punch list." |
| §5 Changes | Verbal change orders allowed | Medium | "All changes require a signed written change order stating price and schedule impact." |
| §7 Liens | No lien waivers mentioned | Medium | "Contractor provides conditional/unconditional lien waivers from itself and major suppliers with each draw." |
| §9 Delays | No completion date | Medium | Ask for target completion window and remedy. |
| §12 Insurance | Not referenced | Medium | Request certificates naming homeowner as certificate holder. |
| Business-terms review only — discuss with a licensed attorney in your state if needed. |
Bluefin: 1) Can you cap rock excavation or give an hourly rate and maximum? 2) Can the draw schedule follow completed stages? 3) Will you provide lien waivers with each draw? Coral: 1) Please price 650 sq ft of decking. 2) What are the pump, filter, and heat pump model numbers? 3) Please include electrical and gas or name the subcontractor and price. Summit: 1) What is the price difference for standard plaster? 2) What's excluded from the 10-year shell warranty?
License lookup, insurance certificates, business registration, complaint history, and three recent local references — to be completed for each builder (state board links are provided in real reports).
FICTIONAL EXAMPLE. In real reports: independent document and price review only; not engineering, structural, inspection, or legal advice; not a recommendation to hire any contractor. Lucan Ashvere is a trade name operated by MB Skydis.